Every manufacturer faces the same question every week: what do we need to buy or make, how much, and when? Order too early and cash sits on the shelf. Order too late and the line stops while a customer waits. Material requirements planning, or MRP, is the method most manufacturing systems use to answer that question systematically.

MRP has been around for decades, and nearly every manufacturing ERP includes it. Yet many small and mid-sized manufacturers either do not use it or do not trust what it tells them. Usually the problem is not the logic. It is the data feeding it. This article explains how MRP works, what it needs, how to make its suggestions reliable and what to look for when choosing MRP software.

What MRP does

MRP takes what you need to deliver (demand), compares it with what you have and what is already on order (supply), and calculates what else must be purchased or produced, and by when. Its outputs are planned orders and action messages: buy this, make that, expedite this order, push that one out, cancel the other.

MRP deals with dependent demand, meaning the components and subassemblies whose need is driven by a finished product. If you plan to build 100 bicycles, you need 200 wheels. Nobody forecasts wheels separately; they are calculated from the bicycle plan.

The three core inputs

  1. Master production schedule (MPS). What finished goods you plan to produce and when. It is built from customer orders, forecasts and inventory targets.
  2. Bill of materials (BOM). The recipe for each product: every component, its quantity per parent and its level in the product structure.
  3. Inventory records. On-hand quantities, open purchase orders, open production orders, allocations, plus planning data for each item such as lead time, lot size and safety stock.

If any of these is wrong, MRP output will be wrong, quickly and confidently.

How the calculation works

MRP processes the BOM level by level, from finished goods down to raw materials. For each item and time period, it performs the same steps:

  1. Gross requirements: total demand for the item in that period, from the MPS or from parent planned orders.
  2. Net requirements: gross requirements minus projected on-hand inventory and scheduled receipts, plus any safety stock you want to keep.
  3. Lot sizing: rounds the net requirement to an order quantity based on rules such as lot-for-lot, fixed quantity, minimum order or a set number of periods of supply.
  4. Lead time offset: moves the order release date back by the item’s lead time so it arrives when needed.
  5. Explosion: the planned order for a parent becomes the gross requirement for its components, and the process repeats at the next level.

A worked example

A hypothetical shop builds a cabinet. Each cabinet uses 4 hinges. The plan calls for 50 cabinets in week 4 and 60 cabinets in week 6. Hinge planning data: 120 on hand, a scheduled receipt of 100 in week 2, a lead time of 2 weeks, a fixed order quantity of 250 and no safety stock.

Gross requirements for hinges are 200 in week 4 (50 x 4) and 240 in week 6 (60 x 4).

Hinges Wk 1 Wk 2 Wk 3 Wk 4 Wk 5 Wk 6
Gross requirements 0 0 0 200 0 240
Scheduled receipts 0 100 0 0 0 0
Projected on hand (starts at 120) 120 220 220 20 20 30
Net requirements 0 0 0 0 0 220
Planned order receipts 0 0 0 0 0 250
Planned order releases 0 0 0 250 0 0

Week 4 is covered by on-hand plus the scheduled receipt, leaving 20. In week 6, demand of 240 against 20 on hand creates a net requirement of 220. The fixed order quantity rounds it to 250, and the two-week lead time means the purchase order must be released in week 4. After week 6, 30 hinges remain.

Common lot-sizing rules

Rule How it works Good fit for
Lot-for-lot Order exactly the net requirement Expensive or custom items
Fixed order quantity Always order a set amount (or multiples) Items with case packs or setup costs
Minimum/maximum Order at least a minimum, never above a maximum Supplier minimums, storage limits
Period order quantity Cover a set number of weeks of demand Low-cost, frequently used items

Why MRP output gets ignored

When planners stop trusting MRP, they fall back to spreadsheets and gut feel. Typical causes include:

  • Inaccurate inventory. If the system says 500 and the shelf holds 300, every suggestion is off.
  • Outdated BOMs. Engineering changes that never made it into the system create shortages of new parts and excess of old ones.
  • Unrealistic lead times. Default or stale lead times produce orders that arrive late or far too early.
  • Late transaction posting. Receipts, issues and production completions recorded days later leave MRP working from yesterday’s picture.
  • A noisy master schedule. If the MPS changes constantly, MRP generates a flood of reschedule messages nobody can act on.

Making MRP work in practice

  1. Fix inventory accuracy first. Use cycle counting, focusing more often on high-value and high-usage items, and investigate the root cause of discrepancies.
  2. Control BOM changes. Route engineering changes through a defined process with effective dates.
  3. Review planning parameters regularly. Compare actual supplier and production lead times with what is in the system and update them.
  4. Stabilize the near term. Use a frozen or firm zone in the MPS so the next few weeks are not constantly reshuffled.
  5. Run MRP on a regular cadence (daily or weekly) and work the action messages, starting with the most urgent.
  6. Remember capacity. Basic MRP assumes unlimited capacity. Use capacity requirements planning or a scheduling tool to check that planned work orders fit your machines and labor.

Choosing MRP software for a small manufacturer

Many small shops plan materials in spreadsheets, and with a handful of products and shallow BOMs that can work. The spreadsheet starts to break down when BOMs have several levels, components are shared across many products, lead times vary by supplier or the master schedule changes every week. Warning signs include frequent shortages despite plenty of inventory overall, expediting as a routine activity and a single planner whose workbook nobody else can update. At that stage, MRP software, whether a standalone planning tool or the MRP module of a manufacturing ERP, is worth evaluating.

Must-have features:

  • Multi-level BOMs with revision control and effective dates
  • Item-level planning parameters: lead time, lot-sizing rule, safety stock, order minimums and multiples
  • Timely inventory, purchasing and production transactions, ideally supported by barcode scanning
  • Clear action messages (release, expedite, defer, cancel) that planners can filter and work through
  • Pegging, so you can trace a component requirement back to the customer order or forecast driving it
  • A firm or frozen zone for the master schedule
  • At least basic capacity visibility, or integration with a scheduling tool
  • Integration with accounting so inventory quantities and costs stay consistent

Questions to ask in a demo:

  1. Can you run MRP on a sample of our own items and BOMs and walk through the output?
  2. How long does an MRP run take, and can it run on demand as well as on a schedule?
  3. How are engineering changes handled for orders that have already been released?
  4. What does data migration involve for items, BOMs, routings and open orders?
  5. How does the system treat capacity: ignored, reported or actively scheduled?

Pricing models usually combine a subscription per named or concurrent user, sometimes with lower-cost licenses for shop floor or view-only users; tiered editions that unlock modules such as capacity planning or quality management; and an implementation fee covering configuration, data migration and training. Ask exactly what is included in each tier and what counts as a billable user.

Red flags include demos that rely only on polished sample data, no clear answer on how inventory accuracy is maintained, implementation plans that skip data cleanup, and promises that software alone will fix planning problems actually caused by inaccurate records.

Key takeaways

  • MRP calculates what to buy and make, and when, from the master schedule, BOMs and inventory data.
  • The logic is simple: gross to net, lot size, offset by lead time, then explode to the next level.
  • Bad data, not bad math, is the usual reason MRP is ignored.
  • Inventory accuracy, current BOMs and realistic lead times are the foundation.
  • Pair MRP with a capacity check and a stable near-term schedule for plans people can actually follow.
  • When evaluating MRP software, test it on your own BOMs and data, and plan for data cleanup as part of implementation.